Electronics supply chain woes - tips to surviving the worldwide crunch

Electronics supply chain woes - tips to surviving the worldwide crunch

November 2022

By Paul Bearpark, Head of Electronics and Software at 42T

For electronics design engineers, recent supply chain issues have added an additional burden to the challenge of meeting demanding specifications in a short time

Not only might a design have to be achieved using components which aren’t the most preferred but it’s been necessary to assess whether the selected components will continue to be available.

Repairman,Disassembling,Laptop,Motherboard.,Engineer,Fixing,Broken,Computer,At,Work.

 

Head of Electronics and Software at 42T, Paul Bearpark, shares design tips that will help you get ahead of ongoing supply chain issues in New Electronics magazine.

Routinely designing in flexibility within a design is certainly beneficial. Not least because it provides the potential to reduce component cost."

Additionally, there’s been significant effort expended to keep existing products in production through redesigns using alternative components where this has been possible.

Paul has put together guidelines on how to survive. He talks over BOM/procurement tips, PCB-design tips, production strategy tips and how to be prepared for anything in this article.

Unprecedented time of supply chain issues

The last 18 months have been extraordinary for the electronics industry. Supply chain issues have dominated everything. For those of us who have been in the industry for a long time we have seen supply issues in the past but never anything remotely on this scale.

As design engineers we have grown very accustomed to being able to design in the best part for the job. So it’s been quite a shock to find that your favourite supplier of microcontrollers is estimating that they won’t have any availability for the next 96 weeks. Initially, it was problems with supply of microcontrollers that made itself felt, and then many other components became infected with the ‘long lead-time’ virus.

Pricing is also an issue

Not only has availability been an issue but prices have also been volatile. We’ve seen significant prices changes even from day to day. On a monthly basis, prices have been seen to change by a factor of ten. This compounds the challenges of component selection - not only are there fewer choices but it’s difficult to be certain about the cost of the bill of materials.

The automotive industry is the one that we seem to hear about the most. Its woes are characterised as being self-inflicted because it cancelled orders with suppliers when lockdowns hammered sales of vehicles. When the economy opened up again, it tried to reinstate those orders only to discover the stock had been reallocated. However, all parts of the electronics sector have been impacted by the semiconductor industry’s inability to respond to rapidly changing demand.

For electronics design engineers the supply chain issues have added an additional burden to the challenge of meeting demanding specifications in a short period of time. Not only might a design have to be achieved using components which aren’t the most preferred but it’s been necessary to assess whether the selected components will continue to be available. Additionally, there’s been significant effort expended to keep existing products in production through redesigns using alternative components where this has been possible.

Adapt to survive

During this period, we have had to adapt and figure out new ways of working. We may even have had to learn some new tools in order to use a different supplier’s components to the ones we are used to. This is especially the case for microcontrollers where completely new toolchains may need to be learned.

We’ve become used to confirming the use of a part once we have ordered and received sufficient parts for first prototypes, subsequent prototypes and even pre-production. We’ve also become much more used to working more closely with purchasing departments at a much earlier stage in the development process so that they are able to start securing stock for production.

In our situation, where most of our designs are developed by contract electronic manufacturers (CEMs) those relationships have had to be put in place much earlier than usual so that they can start securing supplies.

Occasionally, parts that we thought were in stock in sufficient volume turn out to have purchase restrictions on them so that it’s only possible to buy a fraction of the advertised stock.

Designing in flexibility

We’ve started creating designs which have multiple overlapping PCB footprints so that we can quickly change production to use alternative parts in the event that the preferred one becomes unavailable. Alternatively, we have created surface mount modules with a microcontroller or other component on it that can be more easily swapped out than modifying the layout of the main PCB.

PCB boards stacked in a row being picked up by a disembodied hand

Often, we’ve bought devices much sooner and in larger quantities than we would have done before. We appreciate that this could be deemed to be exacerbating the supply problem. But usually the volumes are insignificant compared with the eventual production volume. Hence, we don’t feel that we’re rushing into the supermarket and buying everything on the shelves.

We have frequently discovered that there is only a subset of the previously available variants of a device. In particular, it’s often only microcontrollers with the smaller memory sizes that are available.  Sometimes this can result in a significant re-think about the product implementation and even the features that may be supported. Occasionally, there might be a straightforward way to reduce memory usage.

Purchasing professionals always requested that second sources are identified. In the past this has been regarded as a ‘nice to have’. But it has become a much more important consideration during the design. For example, it’s preferable to use op-amps which have ‘standard’ pinouts than ones that are unique.

Tips for Survival

If it feels like an struggle to pinpoint the components you can use in your design, here some tips:

General guidelines

  • Design for increased flexibility
  • Be aware of market trends
  • Buy now

BOM/procurement tips

  1. Ideally, choose components where there are pin-compatible alternatives where at all possible
  2. As soon as possible (even before the BOM is finalised):
    • Identify the critical components
    • Check their recent availability using websites such as Octopart
    • Buy enough stock to cover you for the manufacturing lead time
  3. You can use a tool like Silicon Expert to assess the ‘health’ of your BOM with regard to lifecycle, multi-sourcing, compliance, stock, etc
  4. You're thinking about using a component but not necessarily confirmed its use - buy it anyway!
  5. Do consider buying from non-authorised distributors, but be aware of the risks
  6. If there's no more stock, look at the alternative versions of essentially the same thing. For example, different package, different packing (tape and reel, loose, etc), different plated pins, automotive grade, etc

PCB-design tips

  1. If space isn’t tight, then design the board with alternative components as ‘do-not-fit’. Only the BoM changes when the components change rather than requiring a PCB redesign
  2. If space is tight, leave space on the board around your preferred component, in case the biggest alternative component is needed. The board design will need to be redesigned, but only by moving the track in this local area
  3. In the most space-constrained circumstances, aim to provide overlapping footprints if possible
  4. Put critical components on daughter boards or modules, so only the daughter board changes for alternative components

 Production strategy tips

  • Start discussing plans with purchasing departments as soon as possible
  • Issue BoMs early so that they can start planning for production and securing supply
  • Understand the project and production schedules from the outset so that it’s clear who will be responsible for purchasing what and when. It’s important to know when the builds move from being prototypes under design department control to the responsibility of the manufacturer

Being prepared

There are suggestions that some of the supply chain issues may be easing now, possibly even leading to a glut. But there’s no doubt that some of the lessons learned during this difficult period should continue to be applied.

Designing in flexibility in a design is beneficial not least because it provides the potential to reduce component cost. And it pays to always be prepared. You never know when the next warehouse fire, earthquake or conflict may disrupt the supply of your products key components.


Paul Bearpark

If you would like to find out more please, contact Paul:
answers@42T.com | +44 | LinkedIn: Paul

Paul Bearpark is an experienced engineer, engineering manager and product manager. He has spent over 25 years working in the field of electronics in both product development companies and technology consultancies. During his career he has led the development of products through their entire life-cycle.

He specialises in radio communications, sensor systems and systems engineering. He has worked in the defence and security, telecommunications, and test and measurement industries.